Contractors and suppliers in California can file a lien to recover payment if they are not paid on a construction project. A mechanics lien is a legal instrument that grants a construction company or laborer a security interest in the property. This article explains the mechanics lien regulations, criteria, and deadlines in California.
California lien deadlines for: Prime Contractors
Preliminary notice requirements 20 Days
In California, general contractors must serve a preliminary notice to the construction lender (if any) within 20 days after the initial provision of supplies or labor. A late notification is only valid for work completed within the previous 20 days.
Mechanics lien deadline 90 Days
In California, general contractors (GCs) must file a mechanical lien within 90 days of the project's completion. However, if a notice of completion or cessation was submitted, the time is lowered to 60 days from the day such notification was submitted.
Enforcement deadline 90 Days
In California, the timeframe for enforcing a mechanics lien is 90 days after the claim is recorded. If the owner agrees to extend credit and both the owner and the claimant sign the submitted Extension of Credit paperwork, the enforcement deadline might be extended.
Following an extension, the action to enforce must be initiated within 90 days of the credit's expiration, but no later than one year after the completion of the work of improvement.
California lien deadlines for: Subcontractors, Suppliers & Others
Preliminary notice requirements 20 Days
In California, subcontractors and suppliers must serve a preliminary notice to the owner, prime contractor, and lender (if applicable) within 20 days of the initial provision of supplies or labor. The tardy notification is only valid for work completed during the previous 20 days.
Mechanics lien deadline 90 Days
The timeframe in California to file a mechanics lien is 90 days after the overall completion of the project. If a notice of completion or cessation was submitted, however, the timeframe for subcontractors, suppliers, and other sub-tier parties is lowered to 30 days from the day the notification was submitted.
Enforcement deadline 90 Days
In California, the timeframe for enforcing a mechanics lien is 90 days after the claim is recorded. If the owner agrees to extend credit and both the owner and the claimant sign the submitted Extension of Credit paperwork, the enforcement deadline might be extended.
In this situation, the enforcement action must be filed within 90 days after the credit's expiration, but no later than one year after the completion of the work of improvement.
Here are some commonly asked questions concerning mechanics liens in California, along with answers prepared by construction attorneys and payment specialists.
When is the deadline to file a California Mechanics Lien?
In California, the time for filing a lien on property varies based on the claimant's function and whether or not a "Notice of Completion or Cessation" is filed on the project.
“Direct contractors” — those who directly engaged with the property owner (such as general contractors), the Claim of Lien must be filed at the earliest of the following dates:
90 days following the completion of the upgrade work; or
60 days following the owner's filing of a Notice of Completion or Cessation
The Claim of Lien must be submitted at the earliest of the following dates for all claimants engaged by someone other than the owner:
90 days after the completion of the improvement work; or 30 days after the owner files a Notice of Completion or Cessation.
In California, who may file a mechanics lien?
Furthermore, if the work being performed necessitates a license, the claimant must be licensed in order to file a mechanics lien.
The Contractor's State Licensing Board (CSLB) establishes the state's licensing standards and guidelines for contractors.
Can I add interest, legal fees, or other charges in a California mechanics lien?
If you foreclose on the lien, however, the court may pay the victorious party the money spent for recording the lien, as well as attorney's fees, as costs.
Can my California lien deadline be extended if development on the project is halted?
The mechanics lien dates in California are all computed from the job's completion or cessation. And both “completion” and “cessation” consider circumstances in which work on a project comes to an end.
Is it necessary to provide a valid property description in the California Mechanics Lien?
Where do I register and submit my California Mechanics Lien?
In California, do I need to notarize the mechanics lien form?
Is it necessary for me to provide notification that the lien has been recorded?
In California, how long does a mechanics lien last?
However, in California, if the claimant and the owner agree to provide credit in accordance with California law, the period in which an action to enforce must be begun can be extended. In this situation, the enforcement action must be filed within 90 days after the credit's expiration, but no later than one year after the completion of the work of improvement.
The complaint must be served on the defendant within 60 days after the filing of an action to enforce the lien in the relevant court. Furthermore, proof of service of the summons and complaint on the defendant must be filed with the court within 60 days of service.
If/when I am paid, who cancels the California Mechanics Lien?
If the underlying obligation is satisfied or the period for instituting enforcement of the lien has passed, the claimant may be obliged to cancel the lien and have it erased from the record. If, after receiving a request from the owner, the claimant does not comply, the owner may petition the court to have the claim dismissed. The claimant may be held accountable for the release's attorney expenses.
Is it true that a California lien takes precedence over pre-existing mortgages or construction loans?
No, a California mechanics lien takes precedence over liens that were affixed to the real property after the start of the work of improvement, or that were unrecorded at the start of the work of improvement and of which the claimant was unaware.